Project Overview
The city of Phoenix
has contracted with Achen-Gardner Construction to construct
improvements to Lower Buckeye Road between 35th and 43rd
avenues. Design is nearing completion and construction will begin
in early September,
and is scheduled to be substantially completed in April, 2012.
The Lower Buckeye
Road Improvements Project will include the following improvements to be
constructed (see aerial map at Project
Design page):
35th
to 39th Avenue Improvements:
·
Widening
Lower Buckeye Road to two lanes in each direction with a center turn
lane
·
Bus
pull-outs to the east and west of 35th Avenue
·
New curb,
gutter, sidewalk and lighting
·
Upgrades to
drainage, the Union Pacific Railroad (UPRR) tracks at 37th
Avenue, and SRP irrigation facilities
·
Various
utility relocations
39th
to 43rd Avenue Improvements:
·